Decision point:A mature custom part (FR4 gasket), 12,000 pcs/year, spot price 1.85 USD/pc. Three ways to buy it: monthly spot orders (Plan A), a framework agreement with locked pricing (Plan B), or stockpiling half-year volumes to hedge a price rise (Plan C). What does each cost per year — and when should you switch?

One-line answer:For mature, stable parts, the framework almost always wins. For ramp-up parts and unstable demand, buy spot. Stockpiling only makes sense when a price rise is genuinely likely. Three thresholds:

Question Threshold Where
Sign the framework?Don't if demand drops below the 9,600-pc floor with probability > 38.8%§3, advantage 2,376 ÷ exposure 6,127
Stockpile?Only if the rise probability exceeds 56% (at 15% expected rise)§4, extra carrying 925 ÷ hedge 1,665
Compare unit prices only?No — Plan A hides 1,265 USD/yr (quoting labor 1,080 + carrying 185), 71% of the discount value§2

Precondition first: the framework is stage three of article #100's ordering ladder — it comes only after 3 consecutive lots at Cpk ≥ 1.33 and 12 months without an ECN. Signing a framework during ramp-up is nailing article #100's rework exposure into a contract.

1. Three plans, defined precisely

Plan How it works What the buyer carries What the supplier carries
A Spot ordersQuote and order 1,000 pcs monthly, pay on deliveryPrice-rise risk, monthly quoting laborAlmost nothing — free to decline any order
B Framework pricingSign 12,000 pcs/yr, price locked at −8%, 12 monthly releases, minimum take 80%Take-or-pay if demand falls, ECN renegotiationPrice-rise risk, capacity reservation
C Inventory hedgeNo agreement; buy 6,000 pcs at spot every 6 monthsCarrying cost, obsolescence if the drawing changesPrice-rise risk transfers to buyer inside the stockpile window

No plan is universally best — they are three ways of splitting the same risks between buyer and supplier. The point of the arithmetic is to price each allocation.

2. Plan A: the spot price is not the whole price — 1,265 USD/yr hidden

Plan A's visible cost is the spend itself: 12,000 × 1.85 = 22,200 USD/yr. Two more lines usually stay out of comparison tables:

① Quoting labor. Each spot batch means re-quoting, comparing, approving: 1.5 h × 12 batches = 18 h at 60 USD/h:

18 h × 60 = 1,080 USD/yr

② Inventory carrying. A 1,000-pc monthly batch averages 500 pcs on hand; carrying cost at 20% of value per year (capital, storage, obsolescence):

500 × 1.85 × 20% = 185 USD/yr

Plan A's true annual cost = 22,200 + 1,080 + 185. The 1,265 USD of hidden cost is exactly what unit-price comparisons miss (failure mode 4 returns to this).

What the flexibility buys: switching suppliers monthly, re-cutting orders on any ECN, shrinking with demand. For a ramp-up part, that flexibility hedges the rework exposure article #100 computed — which is why A is the right answer during ramp-up.

3. Plan B: framework saves 2,376 USD/yr — threshold 38.8%

3.1 The benefit side

Sign the framework: 12,000 pcs locked, price locked at −8% (1.85 → 1.702), 12 monthly releases:

Item A (spot) B (framework)
Unit price1.85 USD1.702 USD
Annual spend22,200 USD20,424 USD
Procurement labor18 h (monthly quoting) = 1,080 USD8 h (annual negotiation + contract) = 480 USD
Average inventory500 pcs = 185 USD500 pcs = 185 USD
Total23,465 USD21,089 USD

B saves 2,376 USD/yr over A: discount 1,776 (22,200 − 20,424) + labor saving 600 (1,080 − 480). Carrying cost is identical — the framework locks price and total volume, while the delivery rhythm stays in your hands (the "locked price + phased delivery" structure from article #100's FAQ Q1).

3.2 The risk side: take-or-pay

The supplier grants 8 points because you commit. The standard clause is a minimum take of 80%: if annual demand falls below 9,600 pcs, you pay the difference at the locked price. Worst case (demand halved to 6,000):

Take-or-pay loss = (9,600 − 6,000) × 1.702 = 6,127 USD

3.3 Break-even

Let q be the probability that annual demand drops below 9,600 pcs:

2,376 = q × 6,127
q = 38.8%

If the probability of demand falling below the minimum take exceeds 38.8% (halving scenario), don't sign; below it, sign. How to estimate q:

The other lever: if the minimum take is negotiated down to 60% (7,200 pcs), the same halving scenario costs only (7,200 − 6,000) × 1.702 = 2,042 USD, and the break-even probability rises to 2,376 ÷ 2,042 = 116% — i.e., sign unconditionally. Every step conceded on the take-or-pay floor is worth far more than a step on price.

4. Plan C: stockpiling is price insurance — premium 925 USD/yr

No agreement, bet on inflation: buy 6,000 pcs at 1.85 every six months and run the second half on stock.

Cost: average inventory rises from 500 to 3,000 pcs; carrying cost rises from 185 to 3,000 × 1.85 × 20% = 1,110 USD/yr — an extra premium of 925 USD/yr.

Benefit: realized only if prices rise. If the rise is r after six months, the second half's 6,000 pcs were bought at the old price:

Hedge benefit = 6,000 × 1.85 × r (USD)

Two break-evens (script-verified):

At an expected rise of 15% (benefit 1,665):
p × 1,665 = 925 → p = 55.6% stockpile only if the rise probability exceeds 56%
At a rise probability of 50%:
0.5 × 6,000 × 1.85 × r = 925 → r = 16.7% the rise must exceed 16.7% to pay back

One line: in a normal year (rise within ±5%), stockpiling never pays — it is a tool for a rise you can see coming, for example when the supplier gives 60 days' written notice of a raw-material increase (article #91's 12+3-day lead time leaves enough window for one final stockpile decision). Historical swings in FR4 glass cloth and epoxy prices typically stay within ±10% — in ordinary years choose A or B, not C.

C also carries a precondition A and B don't: the drawing must not move for 12 months. The stockpile is physical — one ECN turns 6,000 old-revision parts into 11,100 USD of dead stock at 1.85 each (failure mode 3).

5. All three on one sheet: the decision matrix

Dimension A Spot B Framework C Stockpile
Annual total cost (this model)23,465 USD21,089 USD23,310 USD + price risk
Who carries price-rise riskBuyerSupplierBuyer inside the window, buyer after
Demand-drop riskNone (shrink anytime)Take-or-pay exposure 6,127 USDNone, but 11,100 USD obsolescence exposure
ECN flexibilityHighestRenegotiate (8 h + change order)Lowest — stock can't follow a drawing
Right forRamp-up / trial partsMature parts (Cpk ≥ 1.33 + 12 months no ECN)Announced rise + frozen drawing + no ECN expected
Right annual volumeAny≥ 3,000 pcs (to amortize 480 USD negotiation)≥ 6,000 pcs (stockpile batch must be effective)

Pick by part status, in one line:

A during ramp-up (#100), B once mature (this article), C only as a one-shot tool when the rise is announced and the drawing is frozen. Never reverse it: B on a ramp-up part contracts article #100's 14.3% change threshold; C on a part that gets ECNs courts 11,100 USD of dead stock — worse than any price rise.

6. Four failure modes

Failure 1: signing the framework while the part is still in ramp-up. Article #100 showed: above a 14.3% ECN probability, don't lock volume — a framework locks it harder. When the ECN hits: renegotiation 8 h × 60 = 480 USD, change order 120–380 USD (per #95/#98), plus rework of delivered lots to the new revision. The three together can exceed the framework's entire 2,376 USD annual saving. Before signing, check #100's transition criteria — 3 consecutive lots at Cpk ≥ 1.33 and 12 months without an ECN; miss either and stay on Plan A.

Failure 2: squeezing the discount until the supplier has no margin left. −8% is the healthy line in this model. Push to −15% (1.5725) and you save an extra 12,000 × 0.1295 = 1,554 USD/yr — and the supplier's response will be to strip steps: skip baking, loosen sampling, swap to cheaper glass cloth. With the escape rate rising from 0.1% to 1.0% and escape loss at 12 USD/pc (per #96):

Added escape loss = 0.9% × 12,000 × 12 = 1,296 USD/yr
Net gain = 1,554 − 1,296 = 258 USD/yr (a year's work for nothing)
One escaped 500-pc lot = 6,000 USD — two years of the "extra discount" gone

The discount floor in framework talks is 8–10%; below that, re-run article #96's tolerance-budget arithmetic on the supplier's capability claims first — inflated numbers are the earliest symptom of a squeezed supplier.

Failure 3: stockpiling into obsolescence. Plan C's 925 USD/yr premium covers carrying cost only, not drawing changes. On a mature part with a 10% ECN probability, the expected dead-stock loss on 6,000 pcs is 10% × 11,100 = 1,110 USD/yr — more than the premium itself, and C is out. All three preconditions must hold simultaneously: rise announced, drawing frozen for 12 months, demand forecast 90%+ confident. Miss one, go back to B or A.

Failure 4: comparing unit prices only. The unit-price ranking is C = A (1.85) > B (1.702); anyone reading only that row concludes "framework = 8% off, spot and stockpile identical." The real ranking by annual total cost: B 21,089 < C 23,310+ < A 23,465. Plan A's 1,080 USD of quoting labor and Plan B's take-or-pay exposure never appear in a unit price. In your annual purchasing review, fill #5's six rows with your own data — far more useful than pinning four suppliers' unit-price lists to the wall.

7. FAQ

Q1 — How does the framework relate to #100's "locked price + phased delivery"?
Same structure, two stages. #100's FAQ Q1 covered the ramp-up compromise: price and total volume locked, delivery rhythm kept in your hands, used when the supplier insists big orders get the discount. This article is the mature stage's full arithmetic: when signing pays, how to negotiate the take-or-pay floor, and at what discount the supplier starts degrading. The precondition is #100's transition gate: 3 lots at Cpk ≥ 1.33 and 12 months without an ECN.

Q2 — We're a small customer — the supplier won't accept an 80% minimum take. How low can we push?
60% is a realistic floor — conceding on the take costs the supplier far less than conceding on price (§3.3: at a 60% take, the break-even probability rises to 116%, i.e., sign unconditionally). Negotiate in this order: take-or-pay floor first, discount second, adjustment formula last (Q4). Price is the supplier's stiffest lever; spend it last.

Q3 — Is the stockpile (6,000 pcs) the same thing as #100's safety stock (one week, 250 pcs)?
No — different magnitudes, different purposes. Safety stock is a lead-time buffer against supplier delays and demand spikes, sized from stockout loss (#100: 71 USD/yr against 240 USD per stoppage). The stockpile is a price hedge against inflation, sized from carrying cost and rise probability. Merging both into one "inventory policy" meeting usually produces something that neither blocks delays nor hedges prices.

Q4 — What about frameworks longer than 12 months?
Don't hard-lock price beyond a year — nobody can forecast raw materials two years out. Standard practice: an index-linked adjustment clause — price tied to published epoxy/glass-cloth indices, adjusted quarterly, capped at ±2% per adjustment and ±8% per year. The buyer keeps the labor saving and capacity reservation; the supplier isn't betting the farm on epoxy two years out. Hard-lock two years of price and you usually harvest failure mode 2.

Q5 — Does this hold at 3,000 pcs a year?
Discount and labor saving scale with volume; the 480 USD negotiation cost is fixed. At 3,000 pcs/yr: discount 444 + net labor saving ≈ 420 → the advantage falls below ~700 USD and is near the margin; below 1,000 pcs/yr the 480 USD of negotiation and contract work eats most of the discount — stay on Plan A. Note the take-or-pay break-even probability (38.8%) doesn't change with volume — exposure and advantage scale together — so "don't sign small" is really about contract overhead, not risk.

8. Send us your annual volume — three ledgers on one sheet

Quotes for annual customers come with the three-plan comparison: your volume, release rhythm and drawing status turned into a one-sheet A/B/C cost table with the take-or-pay exposure, obsolescence risk and the critical volume where the framework starts to pay. Measured Cpk from comparable parts ships with the quote — when to move from spot to framework is a data decision: Contact us