Decision: Sample approved. Annual usage 12,000 pieces. Do you sign one 12,000-piece blanket order for the discount, or place 2,000-piece orders six times? How much safety stock? And what do you "lock" at the supplier?
One-line answer: A blanket order before the process is proven is a bet on an unproven Cpk — paid at a discount. Three numbers:
| Question | Watershed | Where |
|---|---|---|
| Blanket vs phased | Ramp-up ECN probability 14.3% | §2: net discount $400 ÷ rework exposure $2,800 |
| Safety stock or not | Stockout risk above 0.30/yr | §3: holding $71 ÷ line-down $240 |
| Dual-lot rolling vs single | Delivery-delay stockouts above 1.18/yr | §4: extra holding $284 ÷ 240 |
The ordering rhythm in one line: during ramp-up, buy 2,000 pcs per order with a golden sample and a parameter-lock sheet; after 3 consecutive lots at Cpk ≥ 1.33, scale up, negotiate the discount, set the buffer. Lock the process first, the volume second — reversed, the discount savings won't cover the rework.
1. The ramp-up problem isn't price — it's an unfrozen process
Three correct prototypes prove the supplier can make the part. They prove nothing about whether he makes it right lot after lot. #97 calculated: a Cpk 0.83 process (hole ±0.10, mean shifted +0.03) ships 12.4 defective pieces per 2,000, escaping $164 per lot — and 3 prototypes will almost never expose this kind of gradual shift.
So at sample approval you hold exactly one fact: this process can produce a good part. Whether it stays stable — across material lots, die changes, operator shifts — is unknown.
| What you know | What you don't | Ordering response |
|---|---|---|
| Process can make it right (prototypes) | Whether it stays right (Cpk unknown) | Split volume: 2,000 pcs per order |
| Material grade, die number | Whether they'll change | Write into a parameter sheet — lock |
| Sample dimensions | Whether lots will drift | Seal a golden sample, compare every lot |
| $1.42 at the 2,000-pc tier | Whether volume drops it to $1.28 | Don't lock volume yet — after Cpk is proven |
Core principle: during ramp-up you lock the process; once mature, you lock the price. Do both at once and the process lock fails — you've simply bought defective parts at a discount.
2. Blanket order vs phased delivery: 14.3% is the watershed
Suppliers push blanket orders right after sample approval: 12,000 pcs drops the price from $1.42 to $1.28 (−10%), saving $1,680/yr. Hard to refuse — so price the other side of the ledger.
2.1 The discount's true net gain
| Item | Phased (2,000 × 6) | Blanket (12,000) |
|---|---|---|
| Unit price | $1.42 | $1.28 |
| Annual spend | $17,040 | $15,360 |
| Average inventory (half-lot convention) | ≈ 1,000 pcs | ≈ 6,000 pcs |
| Holding cost (20%/yr: capital, warehousing, obsolescence) | $284 | $1,536 |
Discount gain $1,680, minus extra holding ($1,536 − $284 ≈ $1,280): the blanket order's real net gain is about $400/yr — 24% of the headline discount. Inventory eats the other 76%.
2.2 The exposure: one ECN, how many pieces rework?
The ramp-up phase is ECN-prone: burr growth after a material lot change, chamfer interference found at assembly pilot, a downstream design tweak. Let p = probability the ramp-up needs a change; average undelivered-but-locked volume at that moment ≈ 8,000 pcs; rework $0.35/pc (#97):
Expected rework loss = p × 8,000 × 0.35 = 2,800p (USD/yr)
2.3 Breakeven
Net discount gain $400/yr = expected loss 2,800 × p
p = 400 / 2,800 = 14.3%
If ramp-up ECN probability is below 14.3%, the blanket order wins; above, phased wins.
How to estimate p, two references:
- Look at Cpk. A stable process at Cpk ≥ 1.33 (shifted yield 0.0066%) almost never needs a process change; processes in the 0.8–1.0 band live on die adjustments.
- Look at how new the part is. A copy of a legacy drawing rarely changes; a new structural part typically throws 1–2 ECNs during pilot. A part that never got a DFM review (#95: a 46% cost-down was sitting in the drawing) carries ECN probability well above 14.3% — locking volume on it is near-certain rework.
The ordering rhythm:
| Phase | Trigger | Order type | Lot size | Lock simultaneously |
|---|---|---|---|---|
| Ramp-up, lots 1–3 | Cpk unknown | Purchase per lot | 2,000 pcs | Golden sample + parameter sheet (§5) |
| Freeze | 3 consecutive lots Cpk ≥ 1.33 | Dual-lot rolling + renegotiate price | 4,000 pcs | Safety stock (§3) |
| Mature | 12 months without ECN | Annual/framework pricing | 6,000 pcs | Price + shared forecast (framework — separate article) |
3. Safety stock: it costs $71 a year — don't hold a meeting
Low-value parts get "analyzed" into paralysis. Run the numbers once and the answer is obvious:
- Monthly demand 1,000 pcs (12,000 ÷ 12); one week ≈ 250 pcs
- Holding cost of a 250-pc safety stock: 250 × $1.42 × 20% = $71/yr
- Cost of one stockout (new assumption, typical range): expedited freight $90 + line waiting $150 = $240/occurrence
Breakeven: stockout frequency f × 240 = 71
f = 0.30/yr — i.e., if stockouts hit less than once every 3.4 years, skip it
Said the other way: if a stockout is plausible even once in three years, $71 is the cheapest insurance on the shop floor. Delivery delays on custom parts (#91: 12-day production lead time, volatile around peak season and material changes) are normal, not exceptional. For a $1.42 part:
Safety stock = one week of usage. Set it. Skip the meeting. Worst case — all 250 pcs become obsolete — costs $355 on the books, far below one line-down event.
Recalculate the stock level only when: unit price exceeds ~$10 (holding cost rises 7×; compute precisely against stockout loss), or demand seasonality swings beyond ±50% (a fixed buffer fails; switch to rolling forecasts).
4. Dual-lot rolling: the buffer for lead-time variance
After freeze (Cpk ≥ 1.33), single-lot purchasing has a gap: the previous lot is consumed while the next is in transit — zero buffer. A 5-day slip becomes a 5-day stockout.
Dual-lot rolling keeps two lots in play at all times: one in use, one in transit or just landed. The cost is average inventory rising from 1,000 to 2,000 pcs:
Extra holding = 1,000 pcs × $1.42 × 20% = $284/yr
Breakeven: delay-driven stockouts f × 240 = 284
f = 1.18/yr
If lead-time variance causes more than ~1 stockout a year, dual-lot rolling pays. Given the lead-time structure of #91 (12 days production + 3 days transit, two volatile stages), a 12,000-pc/yr buyer getting bitten once a year or more is the base case — so dual-lot rolling is the default after freeze. Together with §3 it forms a two-layer buffer:
| Buffer | Guards against | Cost |
|---|---|---|
| Safety stock, 250 pcs | Demand spikes, a full rejected lot | $71/yr |
| Dual-lot rolling (+1,000 pcs held) | Lead-time slips, logistics exceptions | $284/yr |
| Total | — | $355/yr (2.1% of spend) |
Both layers failing simultaneously (demand spike + full lot rejection at once) is near-zero probability on a frozen Cpk ≥ 1.33 process.
5. More important than volume: golden sample and parameter lock
Phasing only cuts risk into slices; what kills it is pinning the process down. Two near-zero-cost actions at sample approval:
5.1 Golden sample
Take 3 pieces randomly — not cherry-picked — from the approval lot: supplier seals 2, buyer seals 1. Every incoming lot: compare 1 piece visually against the seal + re-measure CTQ dimensions.
| Step | Correct practice | Common mistake |
|---|---|---|
| Sampling | Random 3 pcs from the approval lot — represents the average | Picking the 3 prettiest — the seal becomes an impossible standard |
| Marking | Both parties sign + date + lot no., tamper-evident seal | A plain label anyone can swap |
| Re-check | CTQ dimensions (hole ±0.10, thickness, flatness) + visual | Visual only, no measurement |
| Refresh | Re-seal after any die or material-grade change | Using a seal until the die is scrapped |
5.2 Parameter lock sheet
Write "how these samples were actually made" into a sheet attached to the PO. For a stamping process, minimum content:
| Parameter | Example | Why lock it |
|---|---|---|
| Die number | Die D-07, clearance 0.05 mm | Clearance drives hole burr and the size distribution (#97's Cpk 0.83 was a clearance problem) |
| Material grade & lot | FR4 3240, grade A, glass orientation 0°/90° | New grade = new punching force = new distribution |
| Stroke rate | 40 strokes/min | Speed affects heat and burr |
| Conditioning | 24 h climate-controlled storage before machining | Moisture affects flatness 0.4 mm/100 mm |
| Inspection plan | Per #97: AQL n=125/Ac=3 | Changing the plan requires written consent |
One rule: any change to this sheet requires a written ECN from the supplier and written approval before it takes effect. A verbal parameter change voids the contract.
What's that worth? #97 again: a silent 0.03 mean shift drops Cpk from 1.33 to 0.83 and costs $985/yr in escapes — and most such shifts start with someone "just tweaking the die." The parameter sheet plus ECN cuts the chain at its source.
6. Four failure modes
Failure 1: taking the discount during ramp-up — 12,000 pcs locked. Net gain $400/yr; one ECN's expected loss tops $2,800. The right moment for the discount negotiation is after 3 lots at Cpk ≥ 1.33 — the process is proven, and your data makes you a stronger negotiator anyway.
Failure 2: sealing the three prettiest samples. A golden sample is the ruler for lot-to-lot drift. A cherry-picked seal makes every normal lot "look wrong" and triggers meaningless rejections; worse, the supplier adjusts the process backwards to match the seal — an imaginary standard degrading a good process. Sample randomly; you want the average, not the ceiling.
Failure 3: the parameter sheet signed, then ignored for six months. Parameter locks rarely fail through malice — they fail through handover: new shift leader, new die, new material lot, nobody opens the sheet. The fix isn't more supervision; it's putting the sheet version on every PO: each order reconfirms "parameter sheet Vx.x — no changes." One line, zero cost, converts "forgot" into "must declare."
Failure 4: safety stock set as a round month of usage. "Let's hold 1,000 pcs — exactly one month." Holding cost $284/yr, four times the calculated level. Safety stock on low-value parts is derived from stockout loss (§3: $71 guarding a $240 event), not from what's easy to remember. A month of a $1.42 part is $1,420 parked on a shelf buying no additional protection — anything beyond a week of usage only guards against "forgot to order," which is an ERP reminder problem, not a cash problem.
7. FAQ
Q1 — The supplier says the price break only applies to one order, and phased orders carry a surcharge — what now?
Ask how large the surcharge is and what locks the price. The common middle ground: framework pricing + phased delivery — sign 12,000 pcs at the discount, deliver in 6 lots. Price and total volume locked, but the delivery rhythm stays in your hands; on an ECN, undelivered portions can be revised. One risk tier below full delivery, and acceptable during ramp-up. (The full framework-agreement math follows in a separate article.)
Q2 — Is a golden sample the same as an FAI report?
No. FAI is a document (full-dimension measured data; #97 requires un-toleranced dimensions too); the seal is a physical artifact. They complement: FAI proves what that lot achieved, the seal gives every future lot something to compare against. Without a seal, how do you prove drift three months later?
Q3 — Doesn't the parameter lock prevent the supplier from improving the process?
No — the improvement channel is the ECN. The rule isn't "no changes," it's "no silent changes." A supplier proposing an ECN to improve yield (#97's die-clearance fix, paid back in 2.3 lots) is welcome: confirm in writing, bump the sheet version.
Q4 — How many lots until "ramp-up" is over?
Judged by data, not the calendar: 3 consecutive lots, ≥ 30 pcs CTQ each, Cpk ≥ 1.33 (the submission obligation in #97). Three months if fast, six if slow. The only legitimate reason to scale up early is a demand-side jump at the customer — that's a different calculation.
Q5 — My annual volume isn't 12,000 — do the conclusions still hold?
Yes; every threshold is recomputable. Substitute your volume and rerun the same formulas. At 3,000 pcs/yr (250-pc lots), the discount nets only $105/yr and the breakeven ECN probability falls to 3.7% — the smaller the volume, the less you should lock volume.
8. Send the drawing — we'll hand you the ordering plan too
Our first-order quotes come with: a recommended delivery rhythm, the CTQ list, a parameter-sheet template, and measured Cpk data from comparable parts. Freeze evidence (3-lot Cpk) is submitted on schedule — when to lock volume is a data decision: Contact us
Further reading
- #97 First Lot: 100% Inspection or AQL Sampling? — source of every Cpk, escape and rework figure here; the release plan complements the ordering plan
- #91 Lead Time & MOQ for Custom Parts — the 12+3-day lead-time structure behind §3/§4 buffer design
- #95 Twelve DFM Changes Before Quoting — fix the drawing before prototyping and ramp-up ECN probability drops below 14.3%
- #93 CNC vs Laser vs Stamping — a process switch triggers re-sealing and a rhythm reset
- #92 Setting Machining Tolerances for FR4 / G10 / 3240 — the tolerance baseline
- Product pages: FR4 fiberglass sheet, 3240 epoxy board, Custom machining